The Government’s Building Digital UK agency has published their December 2025 update on the delivery progress of contracts that have been awarded under their £5bn Project Gigabit broadband rollout scheme. The update reveals that some 183,380 contracted premises (up from 167,770 in Nov 2025) have so far been covered out of a planned total of 1,002,210.

Just to be clear. The figures in this update are not directly comparable to the figures published in BDUK’s general statistics releases. Today’s report tracks the number of contracted premises to which a supplier has delivered a gigabit-capable connection under the main subsidy scheme, whereas the official statistics include the number of premises that have also received a gigabit-capable connection as a result of any public BDUK subsidy (i.e. that covers other schemes too, like gigabit vouchers etc.).

NOTE: Project Gigabit is technology neutral, although Fibre-to-the-Premises (FTTP) is preferred.

At present over 88% of UK premises can already access a gigabit-capable network (here) and Ofcom separately forecasts that this could reach between 91-97% by January 2028 (here). Most of this has been delivered by commercial deployments (predominantly focused on urban and semi-urban areas), but there are some areas in the final 10-20% of premises that are simply too expensive for commercial providers to tackle.

Project Gigabit was originally established in 2021 to help extend broadband ISP networks capable of delivering download speeds of at least 1000Mbps (1Gbps) to achieve “nationwide” coverage (c.99%) by 2030 2032 (here) – focusing on the commercially unviable areas (usually rural and semi-rural locations). The project has already committed most of its budget up to 2030, but there are still some contracts yet to be awarded and others that have been scaled-back or switched suppliers (here, here, here and here).

At this point it’s worth remembering that all of the listed contracts were awarded at different times and are thus at very different stages of development (some started several years apart). A few of the listed contracts have already completed their delivery, such as Wessex Internet’s roll-out for North Dorset and GoFibre’s roll-outs for County Durham and North Northumberland.

Project Gigabit – Contracted Premises and Built Premises by Contract (Dec 2025)

Contract Supplier Contracted premises Built contracted premises
Bedfordshire, Northamptonshire and Milton Keynes CityFibre 21,030 2,460
Bucks, Herts and East of Berks CityFibre 19,090 3,100
CO1 Lancashire, West Berkshire, Staffordshire, Surrey, Hertfordshire, Wiltshire and Gloucestershire Openreach 54,340 8,330
CO2 Devon, Mid Wales and South East Wales Openreach 42,270 4,690
CO3 North Herefordshire, North Wales, Shropshire and South West Wales Openreach 52,060 50
CO4 South Devon, Mid Devon and North Somerset Openreach 37,110 700
CO5 Essex and North East England Openreach 24,710 300
CO6 Rest of Scotland Openreach 65,070 290
CO7 Worcestershire Openreach 22,600 10
Cambridgeshire CityFibre 39,070 7,900
Central Cornwall Wildanet 9,720 6,790
Cornwall and Isle of Scilly Wildanet 14,430 2,240
Cumbria Fibrus 53,540 25,980
Derbyshire Connect Fibre 12,500 330
Dorset and South Somerset Wessex internet 7,240 1,670
Durham GoFibre 4,440 4,440
East Gloucestershire Gigaclear 3,550 590
East and West Sussex CityFibre 41,940 1,730
Hampshire CityFibre 55,570 4,950
Kent CityFibre 46,080 1,570
Leicestershire and Warwickshire CityFibre 38,230 6,980
Lincolnshire and East Riding Quickline 47,800 11,940
New Forest Wessex internet 15,120 7,960
Norfolk CityFibre 48,890 10,000
North Dorset Wessex internet 6,480 6,480
North East Staffordshire Connect Fibre 5,960 1,080
North Oxfordshire Gigaclear 4,180 3,040
North Shropshire Freedom Fibre 3,410 3,410
Northern North Yorkshire Quickline 33,810 5,330
Northumberland GoFibre 3,830 3,830
Nottinghamshire and West Lincolnshire CityFibre 27,820 0
South Oxfordshire Gigaclear 5,310 2,070
South West Cornwall Wildanet 11,120 6,350
South Wiltshire Wessex internet 18,790 3,890
South Yorkshire Quickline 13,290 6,990
Suffolk CityFibre 65,710 13,890
West and Parts of North Yorkshire Quickline 26,310 12,390
TOTAL   1,002,400 183,380

We should point out that CityFibre’s progress under the £58.6m (public subsidy) contract for rural parts of Nottinghamshire and West Lincolnshire (Lot 10) needs to be taken in context, since Connexin originally held this until only a few months ago when they were acquired by CityFibre. Connexin only began the build phase at the end of last year (here), thus its delivery has been stuck in limbo due to that consolidation.

The above is an example of why it’s important to understand the context behind each contract before judging its delivery progress, since a face-value assessment will overlook key realities. Speaking of which, some of the contracted figures may differ from the original announcements, which reflects the usual contract modifications (i.e. the scope of delivery can increase or decrease, such as due to commercial builds by other operators going further than expected or builds costing more than expected etc.).

For some extra context, you can check out the previous figures for November 2025 (here) and October 2025 (here).